A-A+

The project maintains a current and approved s

2022-08-06 04:07:27 问答库 阅读 175 次

问题详情

The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……
A.Monitoring
B.Managing
C.Gathering
D.Reducing

参考答案

正确答案:B
解析:在项目的生命周期里,项目通过如下措施维持一个最新的、经批准的需求集合:
. 管理对需求的变更。
. 维持需求、项目计划和工作产品之间的关联。
. ……

考点: