The customer asks your project to be completed 6 months earlier than planned.You think thi
问题详情
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().
A.balance engineering
B.fast-tracking
C.leveling
D.crashing