()is the process of documenting analyzing tracing prioriiting on requirements and then con

2020-04-21 20:38:42 IT认证 阅读

问题详情

()is the process of documenting,analyzing,tracing,prioriiting on requirements and then controlling change and communicating to stakeholders it is a continuous process throughout a project

A.integratend management

B.configurationmanagemen

C.scopemanagement

D.requirementmanagement

请帮忙给出正确答案和分析,谢谢!

参考答案

考点: