Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule请帮忙给出正确答案和分析,谢谢!
参考答案
正确答案:D