The Estimate Activity Resource process is closely coordinated with the(73) process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
参考答案
正确答案:A
解析:估算活动资源与成本估算是密切联系的。