Estimating schedule activity costs involves de

2022-08-06 03:52:01 问答库 阅读 175 次

问题详情

Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
A.accuracy
B.approximation
C.specification
D.summary请帮忙给出正确答案和分析,谢谢!

参考答案

正确答案:B

考点: