Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().
A.expert judgment
B.analogous estimating
C.requiremen tstraceability matrix
D.three-point estimating请帮忙给出正确答案和分析,谢谢!

参考答案

正确答案:C

考点: