The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)
A.change control board
B. project management office
C.project manager
D.configuration management officer请帮忙给出正确答案和分析,谢谢!

参考答案

正确答案:C
本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。