In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)
A.the quality of the schedule and cost control analysis
B.customer satisfaction
C.customer compromise in defining its needs
D.exceeding customer requirements through gold-plating请帮忙给出正确答案和分析,谢谢!

参考答案

正确答案:B
所有项目中,客户的要求必须根据进度表、成本和有限的资源进行修改。项目的成功主要取决于:A进度表和成本控制分析的优劣B.客户满意程度C客户在确定要求时的折衷态度D通过漂亮的外包装超额满足客户的要求所以答案选B。