● Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.
(74)A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources请帮忙给出正确答案和分析,谢谢!
参考答案
正确答案:D
你的项目由于团队成员之间的冲突而导致进度滞后了,为了解决这种冲突,让项目回到计划进度上来,你应该考虑的是利用临界(应急)资源。