()is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.
A.The control accounts
B.Funding requirement
C.The cost estimates
D.The cost baseline请帮忙给出正确答案和分析,谢谢!

参考答案

正确答案:D

考点: