A-A+ In project network diagram the number of criti 2022-08-06 00:58:35 问答库 阅读 174 次 问题详情 In project network diagram,the number of critical path is().A.noneB.only oneC.only twoD.one or more请帮忙给出正确答案和分析,谢谢! 参考答案 正确答案:D